Compass ceramic pools can be installed in two ways, depending on the type of bottom: flat or inclined.

Sloped bottom pools are installed on the gravel bed, placed both under and around the pool. The subfloor of the pool is washed river gravel (round pebbles) 8-16 mm in size.

Pools with a flat bottom can be installed on the concrete base plate. Once settled, the sides are filled with moistened concrete.

You can see the construction process in the photos - it shows how the Smokey Quartz colored Java pool with sliding roof system is built.

1. Complete manual and construction plans

If you decide to install the Compass ceramic pool, you will receive detailed documentation for the construction company.

Java excavation plan 85

Java excavation plan 85

2. Excavations

After careful measurement, excavations begin.

Compass pool construction - excavations

Compass pool construction - excavations

Installation of a ceramic pool - Earth work with an excavator

Installation of a ceramic pool - Earth work with an excavator

Compass ceramic pool installation – excavation

Compass ceramic pool installation – excavation

 

3. Preparation of the pool subsoil

The bottom of the excavation is filled with a subsoil layer of washed round gravel, poured over a geotextile and compacted. It is also possible to prepare a concrete base plate, but the installation of the Compass ceramic pool does not require this, the gravel bed sufficiently settles the pool.

Ceramic pool installation - gravel bed

Ceramic pool installation - gravel bed

4. Transportation and placement of the pool

The next step is to transport the pool and place it on the base plate or gravel bed.

Swimming pool construction - placing the ceramic pool with a crane

Swimming pool construction - placing the ceramic pool with a crane

Swimming pool construction - settling the pool with a crane

Swimming pool construction - settling the pool with a crane

Installation of ceramic pools Compas Pools

Installation of ceramic pools Compas Pools

 

5. Technological installation and filling

Once the skimmer, inlet nozzles, lights, hoses and pipes are installed, the pool is gradually filled with dry concrete mix or gravel. At the same time, the pool is filled with water to balance the pressure exerted on the walls.

The space under the stairs is always filled with dry concrete.

The space under the stairs is always filled with dry concrete.

Installation of ceramic pools and filling with dry concrete mix

Fill the pool with water JAVA

Fill the pool with water JAVA

6. Installation of the technology in the glass

Once the pool is installed, the installation of the technology begins, either in the pool pit or in a room intended for this purpose (garage, basement, garden shed).

Ceramic pool installation axis and pool technology

Ceramic pool installation axis and pool technology

technology room

technology room

 

7. Pool cover

The deck rails sit on the concrete ring of the pool (if they are to be embedded at floor level), or they sit after the tiles have been laid.

Pool Deck Rail Clearance

8. Tiling around the pool

Placing the tiles around the pool JAVA

Placing the tiles around the pool JAVA

Placing the ceramic pool edge

Placing the ceramic pool edge

9. Installation of the cover

Construction with cover

Construction with cover

Landscaping work in the surrounding area

Landscaping work in the surrounding area

Completed the installation of the JAVA 85 ceramic pool

Completed the installation of the JAVA 85 ceramic pool

 

10. It's done...

...Let's go swimming.

JAVA 85 ceramic pool installation completed - ready for swimming

JAVA 85 ceramic pool installation completed - ready for swimming